ATSE for Data Center Power Switching

In a data center the critical path is usually the UPS, not the changeover. ATSE equipment belongs upstream of the UPS on utility-to-generator transfer, and on the mechanical and support loads that are not UPS protected. Keeping that boundary clear is what prevents avoidable load drops during a utility event.

  • 01

    MOTE Electric ATSE equipment for data center projects is tested to IEC 60947-6-1 and available from 100A to 3200A.

  • 02

    Utility-to-generator changeover at 2000A and above is supplied in PC class with upstream protection handled in the coordination study.

  • 03

    Transfer delay is adjustable per board so mechanical loads do not step the generator beyond its capacity.

Data center server room power supply distribution cabinet with automatic transfer switching equipment
Step 1 — load classes

Which loads need changeover

Group the boards by the loads they serve, then read the tolerated interruption from the most sensitive load on that board.

Loads requiring changeover and their tolerated interruption
Loads requiring changeover and their tolerated interruption
LoadTolerated InterruptionNotes
UPS input (utility / generator)Generator side commonly 10 s – 30 sUPS carries the IT load; ATSE transfers the rectifier input
Chillers and cooling plant≤ 15 s – 30 sLarge motor loads — verify restart current and staging
Cooling pumps and fans≤ 15 sEssential mechanical board with 3P changeover
Lighting and technical rooms≤ 5 sSmall frame changeover at sub-board level
Fire and life safety systemsMeets local life safety ruleDedicated essential board
Office and general servicesNot time criticalDeferred transfer to protect generator capacity
Step 2 — configuration

Typical ATSE configuration

Ratings, poles, class and delay settings commonly used on each board type.

Typical ATSE configuration by data center board
Typical ATSE configuration by data center board
BoardCurrent RatingPolesClassTransfer Time Setting
Utility-to-generator main2000A – 3200A3P / 4PPC1.5 s – 15 s
UPS input changeover1000A – 1600A3P / 4PPC / CC1 s – 10 s
Mechanical essential board400A – 800A3PPC / CC0.8 s – 5 s
Technical room sub-board100A – 320A3P / 4PCC0.5 s – 3 s
Step 3 — design notes

What to settle before the order

Keep the changeover upstream of the UPS

The UPS should remain the ride-through element for the IT load. Placing transfer switching upstream keeps the changeover out of the critical path and avoids nuisance transfers.

Match mechanical load restart to generator capacity

Chillers and pumps draw high restart current. Staging and delayed transfer protect the generator from a step load it cannot accept.

Define the acceptable interruption per board

Not every board needs the shortest transfer time. Setting delay per board preserves generator capacity for the loads that genuinely need fast transfer.

FAQ

Questions on this application

Where should an ATSE be placed in a data center supply?

Upstream of the UPS, on utility-to-generator transfer, and on mechanical and support boards that are not UPS protected. The UPS remains the ride-through device for the IT load.

What transfer time suits a data center main changeover?

Utility-to-generator transfer is commonly set between about 10 s and 30 s, which allows the generator to start and stabilise before the rectifier input transfers.

How do you avoid generator overload during transfer?

Stage the mechanical loads and set different delays per board, so chillers and pumps do not restart simultaneously with the IT support loads.

Does MOTE Electric provide coordinated switchgear for data centers?

Yes. Changeover assemblies can be supplied with the ATSE, bypass, control and signalling integrated in one assembly.

Ask for a configuration review

Send the board schedule and the interruption each board tolerates. We will return a class, rating and delay proposal.